Port machinery

Container handling cranes — repainting without removing the booms

Boom and girder sections too large for a galvanizing bath were blast cleaned in place and coated with cold spray zinc plus a metallic sealer. Work was phased around vessel calls, with two to three girder sections released per shift, so no crane was out of service for a full day.

Port machinery — Container handling cranes — repainting without removing the booms
Representative photograph of this structure type, not a site record of this project.
CorrosivityC5-M
SystemZD96-1 + ZB18-12 sealer
Total dry film120 µm
Coated area23,500 m²

Why hot-dip galvanizing was not an option

Crane girders and cross beams run past forty metres in single pieces, well beyond any galvanizing bath, and dismantling a ship-to-shore crane for transport is not a real option. Meanwhile the terminal keeps working: every day a crane is out of service has a cost measured in berth windows, not in paint. The original zinc-rich epoxy system had served about eight years, with breakdown concentrated where water stands and where the spreader and trolley rails wear the coating mechanically.

System selection

ZD96-1 with ZB18-12 metal sealer, 120 µm total. Thinner than the bridge system on purpose: a ship-to-shore crane sits in marine atmosphere but not in the splash zone, and it has scheduled maintenance access that a bridge over water does not. The metal sealer replaces both intermediate and topcoat — one less coat, which matters because the constraint here is not film build but how many work steps fit into the window between vessel calls.

How it was applied

Work was sequenced around vessel calls: two to three sections per shift, with any section finished during the day taken through to sealer the same day. No bare zinc was left overnight — dew point swings at the quay will start alkaline reaction on an unsealed zinc layer, and the next coat then goes on over a contaminated surface. Scaffolding travelled with the section rather than being built around the whole crane, and blasting used vacuum recovery so grit and dust did not drop onto the rails or into the machinery house.

Acceptance and follow-up

Section-by-section acceptance: thickness and pull-off adhesion per section, released for handover once it passed, so the scaffold came down as work progressed rather than at the end. After the crane returned to service, a visual survey covered the spots that are always missed — under the rails, the machinery house roof, and the tie-rod nodes where water runs down and collects.